Artesia 7 world plan: 95% of fossil electricity replaced, evenings and winter included, no plant in a protected area, electricity for all in 2038, for 10,969 billion euros

If Artesia 7 starts tomorrow, the Earth will switch to renewable electricity on Friday 24 November 2051.
Artesia 7 is a world plan, costed country by country, to replace within 25 years 95% of the electricity produced from coal, gas and oil, and to bring electricity to those who do not have it. It costs 10,969 billion euros, which is 17% of what the world will spend on its armies over the same period, or 52.7 euros per person on the planet per year.

The Artesia 6 plan already answered that question for 10,505 billion. Artesia 7 costs 464 billion more, 4.4%, because it answers questions that Artesia 6 left open: do the plants damage nature? What happens in winter? Can a country depend on a single neighbour? What is a plant worth in a country at war? And what about tomorrow's population? This page starts with these new points, then goes over everything from the beginning for the reader who knows neither the Artesia plans nor the Hydroloop plants.

------------------------------
WHAT ARTESIA 7 ADDS COMPARED WITH ARTESIA 6
------------------------------

QuestionArtesia 6Artesia 7Effect on cost (€bn)
NatureNo check: 3,344 of the 11,354 selected sites touched a protected area or came within 1 km of oneNo plant in a protected area or within 1 km of one, whatever its category: 14,184 candidate sites ruled out of 53,741+1,245
Distance to citiesSites no more than 400 km from a large citySites up to 600 km away, to find good sites again outside protected areas-329
Dependence between countriesNo limit: six countries received all their need from a single supplierA single supplier delivers no more than half of a country's need+23
Less sunny plateausPlateaus from 1,800 hours of sunshine per yearPlateaus from 1,400 hours, with output recalculated hour by hour-348
Mid-latitudesPlateaus searched between 35° south and 35° north7,304 more plateaus, measured between 35° and 50° of latitude-618
WinterThe plan is balanced over the year and over an average dayThe plan is balanced over three periods: winter, summer and the rest of the year+673
Existing damsThey run their turbines in the eveningThey can also hold back up to one tenth of their water from one season to the next-208
Fragile countriesRisk mentioned but not costed; 1,686 TWh exported from countries at warGuarantee paid in advance for the 38 countries on the World Bank list (€70bn); no export plant in a country in conflict for as long as it remains so+175
Population500 kWh per person for today's population500 kWh per person for the population of 2038, the midpoint of the plan+346
Connecting householdsA single price of 1,500 dollars per householdA price based on the actual type of settlement, measured on a 1 km population grid-159
Hours of consumptionCurrent demand (or fully flexible variant)Half of the possible flexibility is counted-336
Total10,50510,969+464

* A more precise plan: the calculation starts from 53,741 measured sites instead of 46,437, of which 39,557 remain possible once protected areas are ruled out; it distinguishes three seasons instead of an average year; it places the people to be connected in seven types of settlement instead of one; and it counts the population of 2038 instead of today's.
* A more reliable plan: four serious objections to Artesia 6 are removed. No plant touches a protected area. No country depends on a single supplier for more than half of its need. No plant intended for export is built in a country at war. And winter, which was not examined, is covered.
* A plan that costs barely more: the new requirements cost 2,462 billion, and the new site searches and finer measurements give back 1,998. The plan remains the cheapest possible for each rule that is set: that is the condition for it to have a chance of being carried out.

The cost of the plan from Artesia 6 to Artesia 7 step by step, the breakdown of spending and the comparison with the world military budget
From Artesia 6 to Artesia 7, step by step; where the money goes; and what the plan represents next to what the world already spends (script: schema_plan_mondial_artesia_7.py)

------------------------------
UNDERSTANDING THIS PLAN WITHOUT KNOWING ANYTHING ABOUT THE SITE
------------------------------

The problem. Nearly six kWh out of ten of the world's electricity still come from coal, gas and oil. Producing it emits about 13 to 14 billion tonnes of CO2 per year, about one third of energy-related emissions. Sun and wind now cost less than these fuels, but they do not produce when we need them: the sun delivers at midday and in summer, whereas consumption is highest in the evening, and often in winter. Replacing fossil electricity therefore means producing enough, and above all storing the electricity of the day to give it back in the evening, and getting through the winter.

The idea. The mulo.world site proposes plants that do both at once: produce with sun and wind, and store with water. The principle is that of pumped-storage hydropower stations, which have existed for a century: two reservoirs at different heights, pumps that raise the water when electricity is plentiful, turbines that bring it back down when it is needed. The water runs in a closed loop. These plants are called Hydroloop.

The plan. Artesia 7 calculates how many of these plants are needed, where to put them, how much they cost and which power lines link them, country by country. It starts from real sites, identified one by one on the world maps of relief, sun, wind, dams and fossil power plants, and an optimisation calculation keeps those that deliver electricity at the lowest cost while respecting all the rules of the plan.

The plants of the plan, in a few words (each name links to its page, in French):
* Hydroloop V14: the large basic plant. Two reservoirs separated by a drop of about 300 m, wind turbines that pump the water upwards, a Pelton turbine that brings it back down in the evening. It is placed on a windy ridge.
* V14 Soleil: the same plant, but with solar panels on trackers instead of wind turbines, on a sunny plateau overlooking a valley. The mixed V14 Soleil also keeps a few wind turbines. It is the most numerous plant in the plan: on its own it produces a little more than two thirds of the electricity of the sites.
* V14 near substations: V14 plants placed on the relief around the substations of the coal, gas or oil power plants that are going to close, in order to reuse their lines (the reusable substations).
* The MAX versions: when a site can carry two, four or six V14, they share a single slope, a single powerhouse and a single substation, and cost up to 10% less (V14 Soleil MAX, V14 MAX).
* V15 Canyon: a storage plant with a very high head, 1,000 to 1,500 m, on the mountain ramparts that overlook large cities.
* V16 Pacha, V17 Gold and V18 Sky: improved V14 plants where the site allows it. The Pacha adds a rain lake above the upper reservoir, whose water goes through the turbines without being pumped; the Gold adds a stream or a spring to it; the Sky adds a lake at the bottom to pump up the surplus of the other plants and keep it for the bad weeks.
* V21 Barrage: a Hydroloop set on an existing dam, with panels or wind turbines; the dam's lake serves as the reservoir. The V22 Saison is the same plant with a season rule: it keeps summer water for the winter in a lake that already exists.
* Muhleisen hybrid solar panel: a solar panel that itself serves as a blade and turns in the wind; it produces by day with the sun and also when there is wind. The plan puts it where it costs less than a plant, and on lakes as floating hybrid islands.
* Titan Claudia towers: city and coastal towers that carry wind turbines and panels, already counted in the plan.

The words of the plan.
* TWh (terawatt-hour): one billion kWh. France consumes about 450 TWh per year, the world about 30,000. GWh: one million kWh. GW: a power of one million kW, that of a large nuclear reactor.
* The evening: from 5 pm to 5 am. This is when the sun no longer produces; the plan must deliver nearly half of consumption during those hours.
* Protected area: national park, nature reserve, World Heritage site, biosphere reserve, Ramsar wetland and all the other areas listed in the World Database on Protected Areas (WDPA), maintained by the United Nations Environment Programme and the IUCN.
* Fragile country: a country on the World Bank's list of fragile and conflict-affected situations (fiscal year 2026): 21 countries in conflict and 17 countries with fragile institutions.
* Flexible demand: a part of consumption shifted from the evening to midday, when solar electricity is plentiful (section 7).
* HDI: the United Nations Human Development Index, which combines life expectancy, schooling and income. Low below 0.55, medium up to 0.70, high up to 0.80, very high beyond.
* €bn: billion euros. All costs are investments over 25 years, at 2026 prices.

------------------------------
IN BRIEF
------------------------------

Artesia 7Result
Cost over 25 years10,969 billion euros, or 439 billion per year
Comparison with the world military budget17% over 25 years, or 4.2 years of that budget
Comparison with the fossil fuel burned today for electricity (€917bn per year at world prices)12.0 years of fuel
Comparison with world investment in clean energy (about €1,980bn per year)22% for 25 years
Comparison with direct fossil fuel subsidies (about €1,170bn in 2022)38% of those subsidies, every year for 25 years
Per person on the planet52.7 euros per year, 14 cents per day
Fossil electricity replaced95% in every country, 17,360 TWh per year
Electricity added for the countries that lack it707 TWh per year in 81 countries
People connected by 20381,182 million
Plant sites selected11,594 in 156 countries, none in a protected area
Delivered every evening, from 5 pm to 5 am20.2 TWh
Fossil power kept in reserve5%: 914 TWh per year, of which 700 between December and February
CO2 avoided13.7 billion tonnes per year, plus about 530 million that the added electricity would have emitted with diesel and coal

The comparisons: world military budget of 2,887 billion dollars in 2025 according to SIPRI, about 2,600 billion euros per year and 64,960 billion over 25 years; fossil fuel burned for electricity calculated on the page electricity country by country; investment in clean energy and grids of 2,200 billion dollars in 2025 according to the International Energy Agency; direct fossil fuel subsidies of 1,300 billion dollars in 2022 according to the International Monetary Fund; 8.3 billion people in 2026. Exchange rate: 0.9 euro per dollar.

Code (Python, free): calcul_plan_mondial_artesia_7.py; the maps: cartes_plan_mondial_artesia_7.py; the charts: schema_plan_mondial_artesia_7.py; the results: the sites, the V15, the countries, the lines, the totals; the new data: the candidate sites and the protected areas, the plateaus from 35° to 50°, the population of 2026, 2038 and 2051, the population by settlement type

The previous plans (in French): Artesia 6 | Artesia 5, version 2, human development | Artesia 5, version 1 recalculated | Artesia 5, first version | Artesia 4 | Artesia 3

------------------------------
1. THE RULES OF THE PLAN
------------------------------

The calculation looks for the cheapest plan that respects all these rules at once.

* Replace 95% of each country's fossil electricity, by day as in the evening, in every season. The remaining 5% is kept as a reserve, mainly for winter.
* A floor of 500 kWh per person per year in every country, all consumption included, calculated on the population of 2038, and a connection for every person who has no electricity.
* No plant in a protected area, nor within 1 km of one, whatever the category of the area.
* Sites no more than 600 km from a large city, so that construction sites and lines remain realistic.
* No more than half of a country's need from a single foreign supplier.
* No export plant in a country in conflict for as long as it is on the World Bank list, and a guarantee paid in advance for everything that is built in a fragile country.
* Poor countries first: at almost equal cost, the plant goes to the country with the lowest Human Development Index (selection discount of 25% for a low index, 19% for a medium one, 12.5% for a high one; the discount is used to choose, not to pay).
* Every plant and every line at the price of its country: labour, concrete and steel do not cost the same in Mali and in Japan.

------------------------------
2. THE METHOD, STEP BY STEP
------------------------------

* What has to be replaced: each country's fossil electricity and its price, on the page electricity country by country (CSV).
* What has to be added: each country's consumption (Our World in Data, CSV), the World Bank's electricity access rate (CSV) and the population of 2038 according to the United Nations (CSV).
* The possible sites, all measured: the plateaus of the sun belt (CSV) and those from 35° to 50° of latitude (CSV, script: balayage_plateaux_35_50.py), the windy ridges (CSV), the relief around the substations of fossil power plants (CSV), the existing dams in the sun (CSV) and in the wind (CSV), the reservoirs for the floating islands (CSV), the V15 ramparts (CSV) and the large springs (CSV).
* Sorting by protected areas: each candidate site is checked against the World Database on Protected Areas (CSV) before any calculation.
* The prices: the plants at the price of each country (CSV) and the lines at the price of each country (CSV).
* The optimisation: a single calculation chooses at the same time the plants, the lines between countries, the evening storage and the winter reserve. It chooses among 39,557 sites (53,741 measured, of which 14,184 ruled out to protect nature) and it has three seasons to balance in every country, by day and in the evening.
* Distribution: the connection of households is costed according to the settlement types of each country (CSV, script: population_habitat_pays.py), then the reinforcement of local grids and the guarantee for fragile countries are added.

------------------------------
3. THE RESULT
------------------------------

Billion euros over 25 yearsArtesia 6Artesia 7Difference
Hydroloop plants, dams and floating islands5,8716,442+571
New Sky plants21.3621.54+0.18
Plant connection, domestic lines, reinforcement786765-21
Export lines743805+62
Hybrid panels1,5191,225-294
V15 Canyon1991-198
V14 reservoirs enlarged for the evening8701,109+239
Titan towers, existing Pacha, Gold and Sky, O Sky2152150
Distribution: connecting households and reinforcing local grids280316+36
Guarantee for fragile countries070+70
Total10,50510,969+464
Electricity added, TWh per year464707+243
People connected, millions6961,182+486
Electricity on export lines, TWh per year5,8134,827-986
Delivered every evening, GWh18,41820,202+1,784

* More plants, fewer stand-alone panels: plants go from 5,871 to 6,442 billion. Winter calls for plants that store, and the best sites ruled out to protect nature are replaced by slightly more expensive sites.
* The V15 Canyon almost disappear: 3 instead of 406. The mountain ramparts above cities are very often protected areas, and flexible demand reduces the need for storage near cities. The enlarged V14 reservoirs take over (1,109 billion instead of 870).
* Less trade: 4,827 TWh per year on export lines instead of 5,813. Countries in conflict no longer export, and the cap per supplier spreads the purchases.

------------------------------
4. NATURE FIRST: NO PLANT IN A PROTECTED AREA
------------------------------

A Hydroloop plant occupies a plateau or a ridge, a slope and two reservoirs. A plan for the climate that damaged national parks or protected forests would contradict itself. Artesia 7 therefore sets the strictest rule, with no exception and no possible discussion: no plant in a protected area, nor within 1 km of one, whatever the category of the area, including areas that are only proposed.

Map of the candidate sites ruled out because of a protected area and of the sites selected by the Artesia 7 plan
In red the candidate sites ruled out, in grey those that remain possible, in green those the plan selects (script: cartes_plan_mondial_artesia_7.py)

* What was checked: the 53,741 candidate sites were checked one by one against the World Database on Protected Areas in its November 2026 version. 14,184 touch an area or come within 1 km of one, that is 26%. Among them, 2,969 are in a national park (IUCN category II), 1,966 in a strict nature reserve or a wilderness area (categories Ia and Ib), and more than 1,000 in a World Heritage site.
* What this changes: Artesia 6, which did not make this check, had selected 3,344 affected sites out of 11,354. They carried 5,538 plants and 4,521 TWh per year, nearly a quarter of the plan. Artesia 7 selects none of them.
* What this costs: 1,245 billion if nothing else is changed. The three site searches that follow (up to 600 km from cities, plateaus from 1,400 hours of sunshine, plateaus from 35° to 50° of latitude) give back 1,295 billion: protecting nature ends up costing the plan nothing, provided we search further afield.
* The countries most affected: India, the United States, Russia, Thailand, Germany, France, Spain and Japan, where the relief close to cities is often protected. In India, the plan cuts down no protected forest: the country buys part of its electricity from its neighbours.

------------------------------
5. THE PLANTS OF THE PLAN
------------------------------

The map shows all the selected sites: the V14 Soleil on the plateaus, from Mexico to Iran, Central Asia and China, and now also in Turkey, Spain and the western United States; the ridge V14 in the windy mountains of North America, Russia, Mongolia and China; the V14 near substations, mostly in China, where fossil power plants are going to close; the V21 on existing dams, mostly in the Americas, Europe and China.

Map of the plants of the Artesia 7 plan by type
The plants of Artesia 7, one dot per site; a larger dot carries several plants (MAX versions) (script: cartes_plan_mondial_artesia_7.py)

PlantsArtesia 6 (number)Artesia 6 (TWh per year)Artesia 7 (number)Artesia 7 (TWh per year)
V14 Soleil on plateaus7,5978,06811,24011,497
Mixed V14 Soleil193196163163
V14 on ridges4,2694,2072,6952,633
V14 near fossil plant substations2,9372,6112,6012,312
V21 Barrage in the sun1,012181685107
V21 Barrage in the wind1,136341882204
Floating hybrid islands2,0962571,294157
Hybrid solar panels2,714 TWh2,362 TWh
V15 Canyon (storage)406 V15, 879 GWh3 V15, 6 GWh
Pacha, Gold and Sky among the V142,607 Pacha, 1,225 Gold, 245 Sky2,630 Pacha, 1,236 Gold, 247 Sky

* The V14 Soleil becomes the plant of the plan: 11,240 instead of 7,597. The sun is more regular than the wind from one season to the next at low latitudes, and the new plateaus from 35° to 50° add 3,434 TWh. The windy ridges fall back: many are protected areas.
* The MAX versions: the 16,699 V14 of Artesia 7 occupy 8,417 sites, including 3,150 MAX sites that carry two, four or six V14.
* The Sky remain: 247 V14 have a lower lake of the Sky version. The seasonal calculation does not ask them to carry the winter, since existing dams do it for less, but they keep their role as insurance for the bad weeks with neither wind nor sun.
* The V22 Saison has no dot on the map, and that is intentional: it is not one more plant to build, it is an operating rule applied to dams that already exist (section 8). The V21 dots show the dams that the plan equips with panels or wind turbines.
* The complete list of plants, site by site with their country and nearest city, is in the sites file, where each country is identified by its three-letter code (Kosovo, which has no official one, carries the code OWID_KOS from the Our World in Data dataset); the list of the Artesia 5 plants explains each type.

------------------------------
6. THE EVENING
------------------------------

Producing enough over the year is not sufficient: the electricity has to be there at the moment it is consumed. Every country receives, every day, its daytime share and its evening share. Evening electricity comes from four sources: the water that each V14 pumps up into its reservoirs during the day, the same thing on a larger scale when the reservoirs of a V14 are enlarged, the existing dams that keep their water to run it through the turbines in the evening, and the V15.

Map of the evening storage of the Artesia 7 plan by country
The evening country by country: enlarged V14 reservoirs and existing dams (circles) and V15 Canyon (triangles) (script: cartes_plan_mondial_artesia_7.py)

Delivered every evening, from 5 pm to 5 am (GWh per day)Artesia 6Artesia 7
V14 own storage7,3278,033
Enlarged V14 reservoirs7,9179,698
Existing dams running their turbines in the evening2,3672,465
V15 Canyon8066
Total18,41820,202

The page evening storage country by country details the method.

------------------------------
7. FLEXIBLE DEMAND: ONLY HALF
------------------------------

Part of consumption can change its hour without bothering anyone: car charging, water heaters, irrigation pumps, cold rooms, part of industry. If it moves from the evening to the middle of the day, when the sun produces, the plan has less water to store.

Share of flexibility countedEvening peakConsumption shifted to middayEvening share of demandCost of the plan (€bn)
Noneunchanged051.7%11,305
25%6% lower2% of the day49.6%11,119
50% (Artesia 7)11% lower4% of the day47.5%10,969
75%17% lower6% of the day45.6%10,832
100%22% lower8% of the day43.6%10,708

* Why half: Artesia 6 gave two figures, one without flexibility, the other with full flexibility. The first ignores what is already being done, the second assumes that everyone plays along everywhere. South Africa already shaves about 5% off its peak through its flexibility measures, according to the International Energy Agency. Artesia 7 counts twice that, for a plan that ends in 25 years and that connects new households, equipped from the start with suitable meters and tariffs.
* What this brings in: 336 billion. The reservoirs to be enlarged deliver 9,698 GWh per evening instead of 11,328.
* What is not counted: the cost of the meters and of controlling the appliances.

Charts of the fossil reserve by season and of the cost of the plan according to the share of flexible demand
On the left, the seasons in which the 5% of fossil power kept is used; on the right, the cost of the plan according to the share of flexible demand (script: schema_plan_mondial_artesia_7.py)

------------------------------
8. WINTER
------------------------------

A solar panel produces much less in December than in June as soon as one moves away from the equator, whereas consumption does not fall. A plan balanced only over the year can therefore run short of electricity in winter and have too much in summer. Artesia 7 balances each country over three periods: December to February, June to August, and the rest of the year, each by day and in the evening.

* What this costs: 673 billion if nothing else is done. It is the price of additional plants, placed where winter is better served.
* The winter reserve: the plan replaces 95% of fossil electricity, 5% remains, that is 914 TWh per year. The calculation chooses the season in which it is most useful: 700 TWh between December and February, 71 between June and August, 143 the rest of the year. The gas power plants that remain become a winter reserve.
* Existing dams: a large dam lake holds water for months. The International Energy Agency estimates that the world's hydropower reservoirs store about 1,500 TWh per full cycle, 170 times more than all pumped-storage stations. The plan assumes that each dam can shift up to one tenth of its output from one season to another; the calculation moves 324 TWh per year to the weak season, out of 4,440 TWh of existing hydropower, that is 7%, and the plan saves 208 billion. No structure is built for this: it is an operating rule.
* The V22 Saison: the page Hydroloop V22 Saison shows this principle on an example, the Hoover Dam in the United States: 412 GWh shifted from summer to winter with 1 km³ of the lake located downstream, without any new structure.

------------------------------
9. DEPENDENCE BETWEEN COUNTRIES AND EXPORT LINES
------------------------------

The best sites are not always where electricity is consumed. The plan builds direct-current lines between countries when producing far away and transporting costs less than producing locally. Each line is paid for at the price of the countries it links and loses 1.5% in its converter stations, plus 3% per 1,000 km.

Map of the electricity exchanges of the Artesia 7 plan
Who exports and who imports: in green the countries that sell more than they buy, in red the opposite, in purple the export lines (script: cartes_plan_mondial_artesia_7.py)

* The cap: a single foreign supplier delivers no more than half of a country's need. In Artesia 6, six countries received all their need from a single neighbour: Kuwait, Qatar and Bahrain from Yemen, Bangladesh from Afghanistan, Hong Kong from Myanmar, Singapore from Thailand. In Artesia 7, no country that imports at least 1 TWh per year is in that situation any more: Japan buys from Russia and North Korea, India from Iran, Pakistan and Nepal.
* What this costs: only 23 billion. The plan goes from 135 to 317 lines, smaller and better spread.
* A dependence that already exists: the world has long lived with much stronger energy dependences. In 2021, the European Union received from Russia about 45% of its gas imports and 40% of its consumption. In 2025, that share had fallen back to about 12% of imports: a dependence can be corrected in a few years when a country decides to.
* Each country's choice: the plan looks for the lowest cost in order to have a chance of succeeding. A country that still considers itself too dependent on its neighbours remains free to pay more to produce at home: the sites file shows it where, and at what price.
* What the cap does not do: it limits each supplier, not total imports. The Netherlands, Singapore, Kuwait or Qatar, small and densely populated, still import about nine tenths of their need, from several countries at once.

Artesia 7 moves 4,827 TWh per year over its export lines, with 364 TWh of losses. The top twelve:

FromToTWh per yearGWkm on landkm under the seaBillion euros
MexicoUnited States9582192,2020237.7
IranIndia4971133,188048.9
RussiaJapan367842,074726113.9
PakistanIndia288661,661019.3
RussiaSouth Korea197452,570020.7
MongoliaTaiwan110253,51122518.1
CzechiaGermany10023369015.4
North KoreaJapan942226077925.7
NamibiaSouth Africa90211,21805.2
North KoreaSouth Korea8118438765.8
NepalIndia77181,32104.6
IranIraq681694103.6

All the lines are in the lines file.

------------------------------
10. FRAGILE COUNTRIES: A GUARANTEE, AND AN EXIT RULE
------------------------------

A plant built in a country at war or with fragile institutions costs more to insure and to finance, and it can be destroyed or seized. Artesia 6 mentioned this risk without costing it, and even placed its largest export plants in Yemen, Myanmar and Afghanistan. Artesia 7 takes two decisions.

* A guarantee paid in advance: everything the plan builds in the 38 countries on the World Bank's list of fragile and conflict-affected situations, that is 516 billion euros of plants, lines and grids, is covered by political risk insurance of the kind offered by MIGA, the World Bank subsidiary that insures investments against war, civil disturbance, expropriation and breach of contract. The calculation counts a premium of 2% per year for 15 years, on 90% of the amount, which falls by half on average over the period: 70 billion. MIGA tends to ask 1% per year and the private market 1 to 3%: the rate used is cautious.
* No export plant in a country in conflict: in the 21 countries in conflict on the list, the plan builds only what serves the inhabitants of the country. Artesia 6 had 1,686 TWh per year leaving these countries, nearly three exported kWh out of ten; Artesia 7 has none leaving them.
* The exit rule: this ban is not a punishment. As soon as a country leaves the conflict list, its export plants can be built. Yemen, Afghanistan or Myanmar have some of the best sunny plateaus in the world: peace opens up an export income for them that the plan keeps in reserve for them.
* The countries concerned: in conflict, Afghanistan, Burkina Faso, Cameroon, the Central African Republic, the Democratic Republic of the Congo, Ethiopia, Haiti, Iraq, Lebanon, Mali, Mozambique, Myanmar, Niger, Nigeria, Somalia, South Sudan, Sudan, Syria, Ukraine, Palestine and Yemen; fragile, Burundi, Chad, the Comoros, the Republic of the Congo, Eritrea, Guinea-Bissau, Kiribati, Libya, the Marshall Islands, Micronesia, Papua New Guinea, São Tomé and Príncipe, the Solomon Islands, Timor-Leste, Tuvalu, Venezuela and Zimbabwe.

------------------------------
11. ELECTRICITY FOR ALL, FOR THE POPULATION OF 2038
------------------------------

The plan keeps the floor of Artesia 6: at least 500 kWh per person per year in every country, and a connection for every person without electricity. This is half of the "modern energy minimum" of 1,000 kWh proposed in 2021 by the Energy for Growth Hub: enough for lighting, refrigeration, pumping water, charging, ventilation, and running a school, a clinic and a workshop.

* The population of 2038: a 25-year plan cannot count today's inhabitants. Artesia 7 takes the population of 2038, the midpoint of the plan, in the medium projection of the United Nations. In the countries below the floor, that makes 1,182 million people to connect instead of 696, and 707 TWh per year to add instead of 464. Cost: 346 billion.
* Where these people live: a world population grid at 1 km (GHSL, Joint Research Centre of the European Commission) classifies each inhabited square kilometre into seven types, from urban centre to very low-density rural. In each country, the people without electricity today are placed in the least dense settlement type, and the additional inhabitants of 2038 are distributed like the current population.

Chart of the people to connect by settlement type and of the cost of connecting them
The people to connect according to their settlement type, and the connection price used for each (script: schema_plan_mondial_artesia_7.py)

Settlement typePeople to connect (millions)Price per household (dollars)MeansCost (€bn)
Urban centre224500grid densification21.0
Dense urban128500grid densification12.0
Semi-dense urban44500grid densification4.2
Suburban167500grid densification15.6
Village1981,000mini-grid37.2
Low-density rural3331,300grid extension81.2
Very low-density rural871,000stand-alone system16.2
Total1,182187.4

* Connecting households: 187.4 billion euros, instead of 332.3 with the single price of 1,500 dollars per household of Artesia 6. A household counts 4.8 people. The prices by settlement type are orders of magnitude drawn from electrification studies: about 1,000 dollars per connection for a mini-grid, 1,300 on average for a rural extension, 500 for a connection in an area already served.
* Reinforcing local grids: 129.1 billion euros. The 707 TWh added require about 161 GW of peak power, counted at 800 euros per kW of transformers and low-voltage lines. This is a cautious assumption, not a measured price.

RegionReceiving countriesElectricity added (TWh per year)People to connect (millions)Distribution (€bn)
Africa47611.71,049277.1
Asia1480.110832.7
North America, Central America and the Caribbean96.9102.7
Oceania56.4123.3
South America61.430.8
Total81706.61,182316.5

------------------------------
12. COUNTRY BY COUNTRY
------------------------------

The 62 countries that receive at least 0.3 TWh per year of added electricity, ranked by added electricity. All the countries are in the countries file.

CountryHDI (2025 report)Population in 2026 (millions)Population in 2038 (millions)Access to electricity (%)kWh per person todayAdded (TWh per year)To connect by 2038 (millions)Distribution (€bn)Produced in the country (TWh)Imports (TWh)Invested in the country (€bn)
Nigeria0.560244.9305.361.2165113.4159.943.1150.01.9113.1
Democratic Republic of the Congo0.522118.3166.222.115971.0142.031.777.30.568.4
Ethiopia0.497140.6183.055.422960.5108.029.863.20.954.9
Tanzania0.55573.6100.448.313241.167.219.755.80.046.0
Uganda0.58253.570.051.510729.644.212.538.80.031.1
Afghanistan0.49645.761.385.316023.824.97.826.11.818.7
Yemen0.47043.657.483.612923.523.57.530.50.919.2
Kenya0.62859.272.576.227120.728.78.882.60.045.6
Madagascar0.48733.943.639.47619.431.09.624.80.020.3
Sudan0.51154.169.866.030919.336.59.121.52.218.6
Mozambique0.49337.250.436.047619.037.910.218.24.818.8
Angola0.61640.856.851.141118.737.48.728.50.021.1
Niger0.41929.340.820.18018.335.49.021.00.819.0
Chad0.41621.830.212.01814.727.87.111.16.113.4
Somalia0.40420.628.850.32314.019.25.015.60.412.4
Malawi0.51723.130.415.68413.527.06.518.60.715.7
Burkina Faso0.45924.931.421.713513.126.36.80.016.96.8
Cameroon0.58831.040.972.025113.119.95.615.90.012.3
Mali0.41926.336.154.522312.622.86.510.18.111.5
Côte d'Ivoire0.58233.944.372.431512.121.25.75.014.58.4
Burundi0.43914.919.511.6419.217.93.810.90.09.2
Rwanda0.57815.018.963.9868.29.82.64.84.95.2
Myanmar0.60955.358.076.84028.116.14.719.50.011.6
Benin0.51515.319.957.01607.611.63.11.09.03.7
South Sudan0.38812.615.75.4477.515.13.52.17.34.7
Guinea0.50015.619.751.12736.112.13.489.90.041.1
Haiti0.55412.113.651.3735.97.52.17.20.26.3
Senegal0.53019.625.174.24395.711.43.07.25.66.9
North Koreanot published26.726.657.51,0235.611.32.5167.913.288.0
Pakistan0.544261.4317.795.67665.611.23.6418.20.2178.3
Papua New Guinea0.57611.013.120.54475.511.02.99.90.08.3
Sierra Leone0.4679.111.135.5245.48.12.313.42.78.9
Nepal0.62229.732.694.03725.34.71.891.22.040.1
Zambia0.59522.830.651.17795.210.43.267.50.131.4
Togo0.57110.012.859.22634.27.81.920.30.011.6
South Africa0.74165.873.287.73,6584.08.02.528.0160.616.2
Central African Republic0.4145.88.217.6274.07.31.84.30.14.0
India0.6851,483.01,610.699.51,4233.77.32.0322.4847.2290.8
Liberia0.5105.97.532.51023.25.71.50.03.81.5
Zimbabwe0.59817.421.762.07273.26.32.08.20.75.0
Mauritania0.5635.57.450.34582.44.81.32.31.92.5
Eritrea0.5033.74.754.41271.92.80.816.00.07.6
Ghana0.62836.043.689.56341.83.61.210.57.55.7
Republic of the Congo0.6496.78.851.38501.53.10.76.10.03.5
Syria0.56426.933.988.49841.42.90.926.30.710.8
Guinea-Bissau0.5142.32.940.5361.42.00.60.01.70.6
Gambia0.5242.93.666.91851.31.80.50.02.00.5
Philippines0.720118.2128.598.01,0541.22.30.7130.10.056.6
Libya0.7217.68.573.24,6861.02.00.634.42.516.4
Indonesia0.728289.0309.899.41,3140.81.70.5331.90.0141.1
Lesotho0.5502.42.757.32480.81.40.519.80.010.0
Peru0.79435.138.596.21,7490.71.30.425.30.09.2
Namibia0.6653.23.956.71,3330.71.30.4102.60.345.3
Cambodia0.60618.220.395.01,2540.50.90.33.14.82.9
Solomon Islands0.5840.91.181.31340.40.40.20.00.30.2
Bangladesh0.685178.9200.599.56720.40.90.32.286.34.4
Comoros0.6030.91.189.81650.40.30.10.60.00.4
Nicaragua0.7067.18.188.37840.40.80.22.70.81.5
Colombia0.78854.258.398.71,7150.30.70.247.60.017.4
Timor-Leste0.6341.41.7100.03640.30.30.10.90.00.5
Equatorial Guinea0.6742.02.666.97870.30.60.13.00.01.6
Botswana0.7312.63.176.01,8520.30.60.23.40.41.7

* Nigeria will have 305 million inhabitants in 2038. The plan connects 160 million people there, adds 113 TWh per year and invests 113 billion euros; the country produces 150 TWh at home and imports almost nothing.
* The Democratic Republic of the Congo, Ethiopia, Tanzania and Uganda follow: together 202 TWh added and 361 million people to connect.

The 25 countries where the plan invests the most:

CountryNeed under the plan (TWh per year)Plants in the plan (number)Produced by the sites (TWh)Hybrid panels (TWh)Exports (TWh)Imports (TWh)Invested in the country (€bn)Export revenue (€bn per year)
China5,8935,6104,3551,91946402,9831.9
United States2,4581,9251,545009221,1040.0
Mexico2521,2271,29309584876638.3
Russia7321,4311,38511576862123.0
Iran3561,0971,1190657047926.3
India1,46137032228308472910.0
Pakistan903994180288017811.5
Saudi Arabia42436840900411760.0
Turkey192399372016801456.7
Indonesia29132233203201411.3
Japan661253217004251280.0
Nigeria1411371500021130.0
Australia1681951760101110.0
Laos12238245021801088.7
Canada14338819004601011.8
North Korea152141681017513887.0
Egypt2041802030216880.1
Malaysia152155156020710.1
Mongolia814314701255705.0
Vietnam1621991670157690.6
Democratic Republic of the Congo717577000680.0
Italy129168136000660.0
Thailand15014813003964611.5
Philippines911271300340571.4
South Korea3581149200258560.0

* China receives more than a quarter of the plan: on its own it burns more than half of the world's coal for its electricity, and it supplies itself almost entirely.
* Mexico, Russia and Iran are the three big exporters: their plateaus and ridges produce far more than their need. Export revenue is counted at 40 euros per MWh.
* India and Japan remain big importers: their best relief is protected or wooded, and the plan does not touch it.

------------------------------
13. WHERE THE MONEY GOES
------------------------------

A plan of this size is also an investment plan: every plant built in a country brings construction work, jobs, and then revenue for decades.

Map of the investment of the Artesia 7 plan by country according to HDI
The money invested in each country over 25 years, in billion euros, according to its Human Development Index (script: cartes_plan_mondial_artesia_7.py)

HDI categoryNeed (TWh per year)Invested, Artesia 6 (€bn)Invested, Artesia 7 (€bn)Produced, Artesia 7 (TWh)Exported, Artesia 6 (TWh)Exported, Artesia 7 (TWh)
Low4959336131,0051,439487
Medium2,1541,1789421,7691,078636
High8,1604,1195,05410,6041,4902,163
Very high6,9693,1613,1035,8091,6521,363
No published index288113125248154177

* The price of caution: low-HDI countries receive 613 billion instead of 933, and medium-HDI countries 942 instead of 1,178. The reason is simple: in Artesia 6, a large part of that money built export plants in Yemen, Afghanistan and Myanmar, three countries in conflict. Artesia 7 now builds there only for the inhabitants. What serves the populations directly increases: the need covered in low-HDI countries goes from 352 to 495 TWh per year.
* The exit rule will give this money back: every country that returns to peace gets its export plants back (section 10).

ContinentNeed under the plan (TWh per year)Plants in the plan (number)Exports (TWh)Imports (TWh)Invested (€bn)
Asia11,66011,0602,1282,4865,523
North America, Central America and the Caribbean2,9533,6711,0681,0172,034
Europe1,7052,6501,0736511,038
Africa1,2941,5455113001,013
Oceania18822022125
South America262421425100

Russia is counted in Europe, Turkey in Asia, Mexico in North America. Investment by country includes the plants, their connection, the hybrid panels, the enlarged reservoirs and distribution; export lines and the plants already counted in the previous plans are not included.

------------------------------
14. WHAT 10,969 BILLION REPRESENTS
------------------------------

ComparisonAmountArtesia 7
World military budget (SIPRI, 2025)about €2,600bn per year17% of that budget for 25 years, or 4.2 years of military spending for the whole plan
World investment in clean energy and grids (IEA, 2025)about €1,980bn per year22% of that investment for 25 years
Fossil fuel burned for electricity€917bn per year12.0 years of fuel: the plan pays for itself with the coal, gas and oil it saves buying
Direct fossil fuel subsidies (IMF, 2022)about €1,170bn per year38% of those subsidies for 25 years
Per person on the planet8.3 billion people in 202652.7 euros per year, that is 4.4 euros per month or 14 cents per day
Per tonne of CO2 avoided13.7 billion tonnes per year32 euros per tonne over the first 25 years, not counting the decades of service that follow
Per fossil kWh replaced17,360 TWh per year63 cents of investment for each kWh replaced every year

* Every year, the plan requires 439 billion euros. The world spends six times more on its armies, and twice as much on the coal, gas and oil it burns in its power plants.
* What the plan does not count as revenue: the fuel saved, the illnesses avoided thanks to cleaner air, the jobs on the construction sites. It counts only what it costs.

------------------------------
15. AFTER THE PLAN: WHAT EVERYONE CAN ADD
------------------------------

Artesia 7 provides a foundation: fossil electricity replaced, evening and winter covered, a minimum for everyone. It does not claim to set the world's consumption for ever. Once this foundation is in place, if the population grows further or if needs increase, everyone can add to it by their own means, without waiting for a new plan.

* Solar panels on the roof of one's house, school or workshop: it is the simplest addition, and the plan's grid is there for the evening.
* A small wind turbine in the garden, where the wind is regular.
* A water turbine in the stream or canal that runs along one's land, for those who have running water nearby.
* Electric cooking: about two billion people still cook with wood, charcoal or kerosene. The floor of 500 kWh is not enough for that. A connected household that adds its own panels can switch to an electric hotplate or pressure cooker, spare the forest and breathe healthier air.
* A country can do the same at its own scale: raise its floor above 500 kWh, or produce more at home in order to depend less on its neighbours.

------------------------------
16. CLIMATE FIRST
------------------------------

* What the plan removes: 95% of each country's fossil electricity, 17,360 TWh per year, about 13.7 billion tonnes of CO2 per year, one third of the planet's energy emissions.
* What the plan avoids: the 707 TWh added, if they were produced with diesel and coal (0.75 tonne of CO2 per MWh), would emit about 530 million tonnes per year. With Artesia 7, this growth is clean from the start.
* What the plan protects: no protected area is touched, no protected forest is cut down.
* What the plan does not do: it does not push consumption beyond the minimum. The aim remains to slow down global warming.

------------------------------
17. WHAT THIS CALCULATION DOES NOT SAY
------------------------------

* The seasons are calculated simply: the share of the sun in each season comes from geometry (the height of the sun according to latitude), without the clouds of each region. The share of the wind in winter is an assumption (30% of annual output between December and February at mid-latitudes). Consumption is assumed to be equal from one season to the next, whereas heating and air conditioning make it vary.
* Dams shifted by a season: the one tenth used is an assumption. The International Energy Agency gives the total stock of the reservoirs, not the share that can really change season in each country.
* The plateaus from 35° to 50°: the output of panels on trackers there is calculated with the same gain as in the tropics (25% more than a fixed panel), which has not been verified at these latitudes.
* Protected areas: the check covers the central point of each site and 1 km around it, not the exact layout of the reservoirs and lines. Each site will require its own local study. A dozen small plants on springs were not checked; they produce 0.4 TWh per year. The world database does not contain all the areas of all countries.
* The guarantee for fragile countries: the rate of 2% per year is cautious, but the insured amount and its decrease over time are assumptions. The World Bank list changes every year, and the Bank revised its classification method in July 2026: the plan uses the list for fiscal year 2026, the last one under the old method.
* North Korea: the calculation looks only at relief, sun, wind and costs. It has 175 TWh per year leaving North Korea, 94 to Japan and 81 to South Korea, which is unrealistic in the current situation, with the United Nations sanctions targeting that country. Without these exports, the same calculation gives 11,039 billion euros, 70 more (setting SANS_EXPORT=PRK in the calculation script).
* Connection: the settlement pattern is that of 2020, applied to 2038 without counting migration to cities; the prices by settlement type are orders of magnitude; a stand-alone system at 1,000 dollars per household supplies less than a grid connection, and it will have to be checked that it reaches the floor.
* Flexible demand: the cost of meters and control is not counted, and the same flexibility is applied to all countries.
* The population after 2038: the plan stops at the midpoint of its duration. Section 15 says how the rest can be done.
* Cooking is not counted (section 15).
* The minimum is a national average: it does not guarantee that every household receives 500 kWh, only that the country has the means to make it so.
* The comparisons use a rate of 0.9 euro per dollar and figures from 2022 to 2025; the world military budget and investment in clean energy increase every year.

------------------------------
CONCLUSION
------------------------------

Artesia 7 costs 10,969 billion euros over 25 years, 464 more than Artesia 6, that is 4.4%. For that difference, the plan no longer touches any protected area, it gets through the winter, it no longer puts any country in the hands of a single supplier, it no longer builds export plants in countries at war and it insures what it builds in fragile countries, and it connects 1,182 million people by counting the inhabitants of 2038. It remains first of all a plan for the climate: 95% of fossil electricity replaced, 13.7 billion tonnes of CO2 avoided every year, for 17% of the world military budget and 14 cents per person per day.

------------------------------
THE PAGES OF THE INVENTIONS OF THE PLAN (IN FRENCH)
------------------------------

Hydroloop V14 | V14 Soleil | V14 Soleil MAX | V14 MAX | V15 Canyon | V15 MAX | V16 Pacha | V17 Gold | V18 Sky | V21 Barrage | V22 Saison | hybrid solar panel | floating hybrid panel | best locations | inventory of inventions | good ideas

------------------------------
SOURCES
------------------------------

The calculation (Python), the maps (Python), the charts (Python), the sites, the V15, the countries, the lines, the totals
Protected areas: Protected Planet, World Database on Protected Areas (WDPA), UNEP-WCMC and IUCN, November 2026 version; only the results of the check are published here (CSV)
Storage of hydropower reservoirs: International Energy Agency, Hydropower Special Market Report, 2021
Flexible demand: International Energy Agency, Demand Response and Scaling Up Demand Flexibility
Fragile countries: World Bank, classification of fragile and conflict-affected situations, fiscal year 2026; the guarantee: MIGA, Multilateral Investment Guarantee Agency
The population of 2038: United Nations, World Population Prospects 2024, medium variant (CSV)
Population by settlement type: European Commission, Joint Research Centre, Global Human Settlement Layer, GHS-POP and GHS-SMOD 2020 grids at 1 km (CSV)
Russian gas in the European Union: Council of the European Union, where does the EU's gas come from
Fossil fuel subsidies: International Monetary Fund, IMF Fossil Fuel Subsidies Data: 2023 Update
Electricity access rate by country: World Bank, indicator EG.ELC.ACCS.ZS, 2023 (CSV)
Consumption by country: Our World in Data, energy data (CSV)
Connection prices: ESMAP, World Bank, "Mini Grids for Half a Billion People", 2019
The modern energy minimum: Energy for Growth Hub
The world military budget: SIPRI, world military expenditure 2025, April 2026
World investment in clean energy: International Energy Agency, World Energy Investment 2025
The Human Development Index: UNDP, Human Development Report 2025 (CSV)
Input data taken from the previous plans: Artesia 6 and section 2

Olivier Muhleisen in collaboration with Claude (Anthropic), November 2026. Plans, diagrams, texts and figures under CC BY 4.0 licence.